Week 1 (July 8) |
Trees cut, outside shingles stripped,
framing begins. |
Week 2 (July 15) |
Rough framing |
Week 3 (July 22) |
Kitchen demolition, rough electrical,
rough framing continues |
Week 4 (July 29) |
Rough plumbing, electrical and plumbing
inspections, plaster prep, boiler replaced (delayed by heating company; happening Aug. 12) |
Week 5 (Aug. 5) |
Board and plaster (didn't happen this week, should happen week 6; electrical, plumbing continued this week) |
Week 6 (Aug. 12) |
Pergo flooring installed in eating area,
kitchen cabinets installed (also boiler replaced - happened Mon, board and plaster scheduled. Pergo hasn't happened yet) |
Week 7 (Aug. 19) |
Cabinet installation cont., trim work,
countertop prep work (Board and plaster work for walls finished this week, cabinets likely next week) |
Week 8 (Aug. 26) |
Trim, countertop work (Cabinets delivered and installed; appliances moved into place; counter template done) |
Week 9 (Sept. 2) |
Tile floor and backsplash installed in
kitchen work area, plumbing and electrical finished, appliances hooked up (Actual: Pergo installed. Counter installation likely week 10, tile floor week 11, backsplash week 12) |
Week 10 (Sept. 9) |
Tile backsplash grouting finished, final
inspection, fabulous new kitchen ready for use. (Actual: Counters, sink, faucet installed) |
Week 11 (Sept. 16) |
Actual: Lots of carpentry work, and work starts putting down our tile floor. |
Week 12 (Sept. 23) |
Installation of tile floor continues, plastic dust shields removed, appliance electrical hookups and backsplash installation. |
Week 13 (Sept. 30) |
Pergo floor uncovered, dryer installed. |