Kitchen Project Calendar

Week 1 (July 8)
Trees cut, outside shingles stripped, framing begins.
Week 2 (July 15)
Rough framing
Week 3 (July 22)
Kitchen demolition, rough electrical, rough framing continues
Week 4 (July 29)
Rough plumbing, electrical and plumbing inspections, plaster prep, boiler replaced (delayed by heating company; happening Aug. 12)
Week 5 (Aug. 5)
Board and plaster (didn't happen this week, should happen week 6; electrical, plumbing continued this week)
Week 6 (Aug. 12)
Pergo flooring installed in eating area, kitchen cabinets installed (also boiler replaced - happened Mon, board and plaster scheduled. Pergo hasn't happened yet)
Week 7 (Aug. 19)
Cabinet installation cont., trim work, countertop prep work (Board and plaster work for walls finished this week, cabinets likely next week)
Week 8 (Aug. 26)
Trim, countertop work (Cabinets delivered and installed; appliances moved into place; counter template done)
Week 9 (Sept. 2)
Tile floor and backsplash installed in kitchen work area, plumbing and electrical finished, appliances hooked up (Actual: Pergo installed. Counter installation likely week 10, tile floor week 11, backsplash week 12)
Week 10 (Sept. 9)
Tile backsplash grouting finished, final inspection, fabulous new kitchen ready for use. (Actual: Counters, sink, faucet installed)
Week 11 (Sept. 16)
Actual: Lots of carpentry work, and work starts putting down our tile floor.
Week 12 (Sept. 23)
Installation of tile floor continues, plastic dust shields removed, appliance electrical hookups and backsplash installation.
Week 13 (Sept. 30)
Pergo floor uncovered, dryer installed.